Your location: Home > News

News

The Environment Requirements of Raised Floor Installation

R-C.jpg

The Environment Requirements of Raised Floor Installation

1. The floor shall be laid after the completion of indoor civil engineering and decoration construction;

2. The ground shall be flat, dry, free of sundries and dust;

3. The usable space under the floor, layout and laying of cables, circuits, waterways, air and other pipelines and air conditioning system shall be completed before the installation of the floor;

4. The fixing of large heavy equipment base shall be completed, and the equipment shall be installed on the base, and the height of the base shall be consistent with the finished height of the upper surface of the floor;

5. 220V / 50Hz power supply and water source are available at the construction site.


CATEGORIES

CONTACT US

Contact: Fred

Phone: 0519-85857638

Tel: 86-18094400616

Email: sales@tonglufloor.com

Add: No.30 Xingchen Road, Hengshanqiao Industrial Park, Changzhou, Jiangsu, China